Project Status
In Progress
Budget
Total: $10,750,000 (Estimated 2024)
Approx $4.5 million will be funded by SDCs and Water Reserve Funds, the remainder will be funded by a loan which the City is still evaluating options.
The City is upgrading the Water Treatment Plant with membrane technology.
Estimated Timeline
Engineering Contract Execution: December 2025
Initiate Funding Program: January 2026
Complete Membrane Purchase: March 2026
Complete 150,000g Clearwell Purchase: April 2026
Complete NEPA Env Review (EA) and Section 106 Cultural Review, if req'd: April 2026
Complete Electrical MCC Purchase: May 2026
Secure Clearwell Building Permit: June 2026
Secure DEQ Backwash Permit: July 2026
Finalize Funding Program: August 2026
Secure OHA Plan Approvals: August 2026
Solicit Construction Bids: September 2026
WTP Construction Notice to Proceed: October 2026
Complete 150,000g Clearwell Construction: December 2026
Initiate New Membrane Operations: March 2027
WTP Substantial Completion: May 2027
Project Close Out: June 2027
Construction Updates
- Contractor starting on demo and build of new Clearwell.
- Membrane equipment is under production.
- Expected timeline:
- 9/2026 Solicit Construction Bids
- 11/2026 Half of the plant processing equipment has been taken offline for decommissioning.
- 12/2026 Complete Clearwell
- 3/2027 Initiate New Membrane Operations
- 5/2027 Substantial Completion
- 6/2027 Project Close Out