Installed a new catch basin in front of Level 11 Salon
Completed pouring the remaining entrance to Conoco
Initiated the laying of the new storm line along SW Main
April 8th - April 12th:
Adjusted water main at 3rd Ave. for new storm lines clearance.
LaRusso completed ¾ of concrete drive work at Sol Tapatio and Conoco drive approaches.
Demolished two existing catch basins and installed one new catch basin.
Re-laid crushed rock base for old bus pad.
Focused on storm work at 3rd Ave.
Worked on storm and irrigation connections.
April 15th - April 19th:
Adjusted two 6” water lines near City Hall.
Installed irrigation valves in the planter area.
Completed new bus pad and last ½ of the drive at Sol Tapatio.
Installed new catch basin near Ace Hardware.
Reconnected storm lines from Ace Hardware parking lot.
Prepped Ace Hardware and Chapmans' entrances.
Installed 70’ of 12” storm line in front of City Hall.
LaRusso was onsite for concrete work at Chapmans and curbs along Phase 4.
S&W Underground crew installed manhole #5.
Prepping concrete for sidewalks in front of State Farm and Level 11 Salon.
April 22nd Traffic Interruption:
Scheduled from 7 am to 5 pm.
S&W Underground and Global Electric will:
Demolish and remove existing concrete crosswalk areas at 3rd Avenue.
Install conduit for future crosswalk signaling enhancements.
April 22nd - April 26th
Demolished the existing concrete crosswalk area at 3rd Ave and the concrete island on Main Street.
Completed the installation of the remaining 1 ½" conduit supplying the RRFB's, along with the ¾" conduit crossing 3rd Ave.
Sidewalks were poured in front of State Farm, half of the Level 11 frontage, and the ADA ramp at the SE corner of 4th Ave by LaRusso.
Lowered the irrigation vault at Ace Hardware.
Prepped sidewalk areas for upcoming concrete work.
Focused on temporarily paving the trenches created on Monday.
Started foundation transition work at Yo Treats, with additional attention required.
Planned activities include placing 12" storm lines to connect various catch basins along the west side of Main Street.
Global Electric will be onsite to pour RRFB foundations and the metered pedestal base.
April 29th - May 3rd
Wrapped up the 12" storm run from Conoco to City Hall
Abandoned existing irrigation vault near 3rd Ave
Potholed utilities in front of Yo Treats
Started catch basin run from manhole #4 near Yo Treats to Catch basin near Kristy's
Poured sidewalks in front of Level 11
Prepped ADA's at NE/NW 3rd Ave
Roughed in channels on manholes #4 and #5
Installing manhole #1
Prepping for final storm runs leading to manholes #2 and #3
Laid out asphalt cut lines for future work
Important Information:
Parking along Main Street will continue to be disrupted during work hours. We apologize for any inconvenience this may cause and appreciate your understanding.
The lot adjacent to Sol Tapatio will be cleaned up to divert traffic from the Sol Tapatio drive-through in preparation for future construction work.
Phase 1 is 3rd to 4th Ave (heading South)
Phase 2 is 4th Ave to the Highway (heading South)
Phase 3 is Jeremy Loveless to 4th Ave (heading North)
Install the new fire hydrant on Phase 2 (4th Ave to the Highway - heading South).
Continue demolition into Phase 4 (4th Ave to 3rd Ave - heading North).
Install conduit/irrigation along Phase 4 (4th Ave to 3rd Ave - heading North).
Commence saw cutting for storm work.
Perform saw cutting for the Main street crossing needed for the 3" PGE power supply.
Finish phase I sidewalks and place curbs along Phase 2 (4th Ave to the Highway - heading South).
Completing demolition on Phase 4 (4th Ave to 3rd Ave - heading North).
Placing conduit/irrigation/junction boxes along Phase 4 (4th Ave to 3rd Ave - heading North).
Trenching for 3" PGE crossing.
Placing curbs along Phase 2 (4th Ave to the Highway - heading South).
March 11th - March 15th:
The demolition of Phase 4 is nearing completion.
Conduit, irrigation systems, and junction boxes have been diligently placed along Phase 4.
Trenching work for the 3" PGE crossing has been successfully completed.
The installation of curbs along Phase 2 is currently underway.
March 18th - March 22nd:
Completed conduit/irrigation installation.
Addressed potholed water main at 3rd Street.
Rectified curb issues identified in Phase 2.
Poured half of the concrete entry into the City Hall parking area and one full entry into Conoco.
Placed curbs along Phase 3.
Completed incidental storm work along Phases 3 and 4.
March 25th - March 29th:
Completed Phase 3 curbs
Prepped and poured roughly 1/3 of the Phase 4 curbs
Prepped Phase 2 and 3 sidewalk areas
Installed 3 incidental rain drains
Demolished the curb and sidewalk on the NE corner of 3rd
Demolished and replaced 1 catch basin at NE 3rd
Filled potholes
Temporarily paved 4 street crossings
Swept the site
Finish the installation of storm manhole #4 near Yo-Treats
Temporarily pave additional ditch lines to address concerns
Continue pouring concrete sidewalks and driveway approaches into City Hall, Conoco, and Sol Tapatio
Temporary pedestrian access may be interrupted on the 29th and into early April while the new concrete sidewalks/driveways are in the curing process
Important Information:
Parking along Main Street will continue to be disrupted during work hours. We apologize for any inconvenience this may cause and appreciate your understanding.
The lot adjacent to Sol Tapatio will be cleaned up to divert traffic from the Sol Tapatio drive-through in preparation for future construction work.
Phase 1 is 3rd to 4th Ave (heading South)
Phase 2 is 4th Ave to the Highway (heading South)
Phase 3 is Jeremy Loveless to 4th Ave (heading North)
S&W Underground worked on upsizing the water lines and trenching areas for electrical, irrigation, and sidewalk installation.
Striving to keep one side of the road open as much as possible to allow traffic flow.
On-street parking in front of Yo-Treats may be unavailable temporarily as they work.
Concrete chipping work was underway on 3rd Street.
The waterline installation is nearing completion and is expected to wrap up by the end of the month. There may be a brief interruption in water service. This will affect Dollar General, Yo-Treats, Backroads Beauty, and City Hall. S&W Underground will be reaching out to the owners of these businesses ahead of time to coordinate and minimize disruptions.
Demolition work starting from Yo-Treats and extending to the end of Main Street, where it meets the highway, commenced. To ensure safety, temporary pedestrian fencing was installed along the affected areas. Access to the bus stop will remain available throughout the process.
Curbing installation started on the 16th.
The Trimet bus stop was reopened on February 16th.
Conduit and trenching work for streetlights commenced the 19th, from Yo-Treats to City Hall.
Progress has been made with curb installations, and additional concrete work is slated to begin soon, particularly at the driveway by McCrae's and Kristy's food truck. Kindly note that on-street parking may be affected throughout the week due to these activities.
Trenching for electrical purposes will commence on 4th Ave between Kristy's and Yo-Treats. Please anticipate potential traffic impacts while traveling along this route.
Demolition work for Phase 3 (Jeremy Loveless to 4th Ave - heading North) is scheduled to commence towards the end of the month, starting from Jeremey Loveless to Sol Tapatio.
Water service interruption on the 26th. They will be transitioning to the new water line, with work starting in the early morning. This is to ensure businesses can open as normal with minimal disruption to their water services. We apologize for any inconveniences and appreciate your patience. Businesses that will be affected are Dollar General, Backroads Beauty, Yo-Treats, City Hall, Sol Tapatio, Conoco (Chevron), and the Fire Department.
Installing the new fire hydrant is planned for last week of the month.
Continuing sidewalk pouring along Phase 1 (3rd to 4th Ave - heading South).
Preparing for curbs along Phase 2 (4th Ave to the Highway - heading South).
Initiating demo/electrical trenching along the Phase 3 portion of the project (Jeremy Loveless to 4th Ave. east side of Main).
Successfully connected both ends of the new water main.
Completed sidewalk demolition along Phase 3 (Jeremy Loveless to 4th Ave - heading North).
Concluded conduit/irrigation trenching along Phase 3 (Jeremy Loveless to 4th Ave - heading North).
Construction has started, S&W Underground has begun the sidewalk demolition leading from Harvest Market towards Clackamas River Growlers. Temporary fencing and pedestrian access to businesses are in place.
The ADA directly behind Harvest Market and driveway into McCrae's Motel is open to allow residents and medical transport in.
Demolition will continue along Main's West side into early February and then transition to the waterline located in the alley behind Sol Tapatio.
Phase 1 is anticipated to be completely demolished and temporary access in place by early February, but we will update with any changes or delays.