April 29th - May 3rd
- Wrapped up the 12" storm run from Conoco to City Hall
- Abandoned existing irrigation vault near 3rd Ave
- Potholed utilities in front of Yo Treats
- Started catch basin run from manhole #4 near Yo Treats to Catch basin near Kristy's
- Poured sidewalks in front of Level 11
- Prepped ADA's at NE/NW 3rd Ave
- Roughed in channels on manholes #4 and #5
- Installing manhole #1
- Prepping for final storm runs leading to manholes #2 and #3
- Laid out asphalt cut lines for future work
May 6th - May 10th:
- Installed catch basin at NE 3rd/Main
- Set Manhole #2
- Installed 46' of 12" storm pipe
- Hauled trench spoils offsite
- Backfilled curb lines
- Addressed potholes on Main Street
- Began saw cutting full depth AC replacement areas
- Global Electric installed electric pedestal
May 14th - May 24th:
- Demolition of asphalt shoulders and full depth replacement near center line. Backfilled with rock for paving preparation.
- Base lifting asphalt shoulders and patching center areas from OR 211/224 to 4th Ave. Lane adjustments made, access still available.
- Top lifting full width of Main St. from OR 211/224 to 4th Ave. Traffic Control Plan 6 will be in place, access restricted.
- Base lifting asphalt shoulders and patching center areas from 4th Ave. to 3rd Ave. Lane adjustments made, access available.
- Top lifting full width of Main St. from 4th Ave. to 3rd Ave. Traffic Control Plan 7 will be in place, access restricted.
May 27th - May 31st:
- Some weather delays led to continuing paving work from 3rd to 4th Street. Traffic Control Plan 7 will be in place, access restricted.
- Installation of RRFB pole at 3rd Ave.