March 4th - March 8th
- Install the new fire hydrant on Phase 2 (4th Ave to the Highway - heading South).
- Continue demolition into Phase 4 (4th Ave to 3rd Ave - heading North).
- Install conduit/irrigation along Phase 4 (4th Ave to 3rd Ave - heading North).
- Commence saw cutting for storm work.
- Perform saw cutting for the Main street crossing needed for the 3" PGE power supply.
- Finish phase I sidewalks and place curbs along Phase 2 (4th Ave to the Highway - heading South).
- Completing demolition on Phase 4 (4th Ave to 3rd Ave - heading North).
- Placing conduit/irrigation/junction boxes along Phase 4 (4th Ave to 3rd Ave - heading North).
- Trenching for 3" PGE crossing.
- Placing curbs along Phase 2 (4th Ave to the Highway - heading South).
March 11th - March 15th:
- The demolition of Phase 4 is nearing completion.
- Conduit, irrigation systems, and junction boxes have been diligently placed along Phase 4.
- Trenching work for the 3" PGE crossing has been successfully completed.
- The installation of curbs along Phase 2 is currently underway.
March 18th - March 22nd:
- Completed conduit/irrigation installation.
- Addressed potholed water main at 3rd Street.
- Rectified curb issues identified in Phase 2.
- Poured half of the concrete entry into the City Hall parking area and one full entry into Conoco.
- Placed curbs along Phase 3.
- Completed incidental storm work along Phases 3 and 4.
March 25th - March 29th:
- Completed Phase 3 curbs
- Prepped and poured roughly 1/3 of the Phase 4 curbs
- Prepped Phase 2 and 3 sidewalk areas
- Installed 3 incidental rain drains
- Demolished the curb and sidewalk on the NE corner of 3rd
- Demolished and replaced 1 catch basin at NE 3rd
- Filled potholes
- Temporarily paved 4 street crossings
- Swept the site
- Finish the installation of storm manhole #4 near Yo-Treats
- Temporarily pave additional ditch lines to address concerns
- Continue pouring concrete sidewalks and driveway approaches into City Hall, Conoco, and Sol Tapatio
- Temporary pedestrian access may be interrupted on the 29th and into early April while the new concrete sidewalks/driveways are in the curing process
Important Information:
- Parking along Main Street will continue to be disrupted during work hours. We apologize for any inconvenience this may cause and appreciate your understanding.
- The lot adjacent to Sol Tapatio will be cleaned up to divert traffic from the Sol Tapatio drive-through in preparation for future construction work.
- Phase 1 is 3rd to 4th Ave (heading South)
- Phase 2 is 4th Ave to the Highway (heading South)
- Phase 3 is Jeremy Loveless to 4th Ave (heading North)
- Phase 4 is 4th Ave to 3rd Ave (heading North)