March 2024

March 4th - March 8th

  • Install the new fire hydrant on Phase 2 (4th Ave to the Highway - heading South).
  • Continue demolition into Phase 4 (4th Ave to 3rd Ave - heading North).
  • Install conduit/irrigation along Phase 4 (4th Ave to 3rd Ave - heading North).
  • Commence saw cutting for storm work.
  • Perform saw cutting for the Main street crossing needed for the 3" PGE power supply.
  • Finish phase I sidewalks and place curbs along Phase 2 (4th Ave to the Highway - heading South).
  • Completing demolition on Phase 4 (4th Ave to 3rd Ave - heading North).
  • Placing conduit/irrigation/junction boxes along Phase 4 (4th Ave to 3rd Ave - heading North).
  • Trenching for 3" PGE crossing.
  • Placing curbs along Phase 2 (4th Ave to the Highway - heading South).

March 11th - March 15th:

  • The demolition of Phase 4 is nearing completion.
  • Conduit, irrigation systems, and junction boxes have been diligently placed along Phase 4.
  • Trenching work for the 3" PGE crossing has been successfully completed.
  • The installation of curbs along Phase 2 is currently underway.

March 18th - March 22nd:

  • Completed conduit/irrigation installation.
  • Addressed potholed water main at 3rd Street.
  • Rectified curb issues identified in Phase 2.
  • Poured half of the concrete entry into the City Hall parking area and one full entry into Conoco.
  • Placed curbs along Phase 3.
  • Completed incidental storm work along Phases 3 and 4.

March 25th - March 29th:

  • Completed Phase 3 curbs
  • Prepped and poured roughly 1/3 of the Phase 4 curbs
  • Prepped Phase 2 and 3 sidewalk areas
  • Installed 3 incidental rain drains
  • Demolished the curb and sidewalk on the NE corner of 3rd
  • Demolished and replaced 1 catch basin at NE 3rd
  • Filled potholes
  • Temporarily paved 4 street crossings
  • Swept the site
  • Finish the installation of storm manhole #4 near Yo-Treats
  • Temporarily pave additional ditch lines to address concerns
  • Continue pouring concrete sidewalks and driveway approaches into City Hall, Conoco, and Sol Tapatio
  • Temporary pedestrian access may be interrupted on the 29th and into early April while the new concrete sidewalks/driveways are in the curing process

Important Information:

  • Parking along Main Street will continue to be disrupted during work hours. We apologize for any inconvenience this may cause and appreciate your understanding.
  • The lot adjacent to Sol Tapatio will be cleaned up to divert traffic from the Sol Tapatio drive-through in preparation for future construction work.
  • Phase 1 is 3rd to 4th Ave (heading South)
  • Phase 2 is 4th Ave to the Highway (heading South)
  • Phase 3 is Jeremy Loveless to 4th Ave (heading North)
  • Phase 4 is 4th Ave to 3rd Ave (heading North)