June 2024

June 3rd - June 7th:

  • Finished the planned paving work along Main Street.
  • Backfilled sidewalk edges near 300 Main/City Hall with blended soil.
  • Installed the remaining street signs, including the new 24/7 crosswalk warning signs, benches, and garbage cans.
  • Connected the irrigation control timer and installed the catch basin near City Hall to address the puddling issue.

June 10th - 14th:

  • Pave the added portion of asphalt along Main Street, connecting our project to the new pavement just to the north (approximately 34' x 34').
  • Complete the transition panels in various areas of town.
  • Begin setting the light poles and RRFB poles (6/11-6/12).

June 17th - 21st:

  • Striping is scheduled for 6/17 and 6/18 (dependent on weather), this will involve some traffic interruption.
  • PGE will be onsite 6/17 to connect the power to the new metered pedestal.
  • General cleanup of the project site.
  • Complete work on Channel 2 manholes.
  • Finish concrete work around light poles and near Ace Hardware.
  • Pour two sidewalk chalk areas.