June 3rd - June 7th:
- Finished the planned paving work along Main Street.
- Backfilled sidewalk edges near 300 Main/City Hall with blended soil.
- Installed the remaining street signs, including the new 24/7 crosswalk warning signs, benches, and garbage cans.
- Connected the irrigation control timer and installed the catch basin near City Hall to address the puddling issue.
June 10th - 14th:
- Pave the added portion of asphalt along Main Street, connecting our project to the new pavement just to the north (approximately 34' x 34').
- Complete the transition panels in various areas of town.
- Begin setting the light poles and RRFB poles (6/11-6/12).
June 17th - 21st:
- Striping is scheduled for 6/17 and 6/18 (dependent on weather), this will involve some traffic interruption.
- PGE will be onsite 6/17 to connect the power to the new metered pedestal.
- General cleanup of the project site.
- Complete work on Channel 2 manholes.
- Finish concrete work around light poles and near Ace Hardware.
- Pour two sidewalk chalk areas.