- S&W Underground worked on upsizing the water lines and trenching areas for electrical, irrigation, and sidewalk installation.
- Striving to keep one side of the road open as much as possible to allow traffic flow.
- On-street parking in front of Yo-Treats may be unavailable temporarily as they work.
- Concrete chipping work was underway on 3rd Street.
- The waterline installation is nearing completion and is expected to wrap up by the end of the month. There may be a brief interruption in water service. This will affect Dollar General, Yo-Treats, Backroads Beauty, and City Hall. S&W Underground will be reaching out to the owners of these businesses ahead of time to coordinate and minimize disruptions.
- Demolition work starting from Yo-Treats and extending to the end of Main Street, where it meets the highway, commenced. To ensure safety, temporary pedestrian fencing was installed along the affected areas. Access to the bus stop will remain available throughout the process.
- Curbing installation started on the 16th.
- The Trimet bus stop was reopened on February 16th.
- Conduit and trenching work for streetlights commenced the 19th, from Yo-Treats to City Hall.
- Progress has been made with curb installations, and additional concrete work is slated to begin soon, particularly at the driveway by McCrae's and Kristy's food truck. Kindly note that on-street parking may be affected throughout the week due to these activities.
- Trenching for electrical purposes will commence on 4th Ave between Kristy's and Yo-Treats. Please anticipate potential traffic impacts while traveling along this route.
- Demolition work for Phase 3 (Jeremy Loveless to 4th Ave - heading North) is scheduled to commence towards the end of the month, starting from Jeremey Loveless to Sol Tapatio.
- Water service interruption on the 26th. They will be transitioning to the new water line, with work starting in the early morning. This is to ensure businesses can open as normal with minimal disruption to their water services. We apologize for any inconveniences and appreciate your patience. Businesses that will be affected are Dollar General, Backroads Beauty, Yo-Treats, City Hall, Sol Tapatio, Conoco (Chevron), and the Fire Department.
- Installing the new fire hydrant is planned for last week of the month.
- Continuing sidewalk pouring along Phase 1 (3rd to 4th Ave - heading South).
- Preparing for curbs along Phase 2 (4th Ave to the Highway - heading South).
- Initiating demo/electrical trenching along the Phase 3 portion of the project (Jeremy Loveless to 4th Ave. east side of Main).
- Successfully connected both ends of the new water main.
- Completed sidewalk demolition along Phase 3 (Jeremy Loveless to 4th Ave - heading North).
- Concluded conduit/irrigation trenching along Phase 3 (Jeremy Loveless to 4th Ave - heading North).