Are we too far into the design to consider relocating the Public Works Shops elsewhere to preserve the open space/park land adjacent to the river?

The location is chosen to be the lot that the city owns. We are too far along in the process to change locations. However, the layout is still in design stages so it is the perfect time to consider the best use and arrangement of the current PW buildings and the exact location of the wastewater facility on the City lot. We evaluated building the WWTP on the Public Works shops and rebuilding the shops elsewhere on the same lot. This would add at least $5 million to the project cost.