April 1st - April 5th:

  • Poured sidewalk areas near Yo Treats
  • Installed a new catch basin in front of Level 11 Salon
  • Completed pouring the remaining entrance to Conoco
  • Initiated the laying of the new storm line along SW Main

April 8th - April 12th:

  • Adjusted water main at 3rd Ave. for new storm lines clearance.
  • LaRusso completed ¾ of concrete drive work at Sol Tapatio and Conoco drive approaches.
  • Demolished two existing catch basins and installed one new catch basin.
  • Re-laid crushed rock base for old bus pad.
  • Focused on storm work at 3rd Ave.
  • Worked on storm and irrigation connections.

April 15th - April 19th:

  • Adjusted two 6” water lines near City Hall.
  • Installed irrigation valves in the planter area.
  • Completed new bus pad and last ½ of the drive at Sol Tapatio.
  • Installed new catch basin near Ace Hardware.
  • Reconnected storm lines from Ace Hardware parking lot.
  • Prepped Ace Hardware and Chapmans' entrances.
  • Installed 70’ of 12” storm line in front of City Hall.
  • LaRusso was onsite for concrete work at Chapmans and curbs along Phase 4.
  • S&W Underground crew installed manhole #5.
  • Prepping concrete for sidewalks in front of State Farm and Level 11 Salon.

April 22nd Traffic Interruption:

  • Scheduled from 7 am to 5 pm.
  • S&W Underground and Global Electric will:
    • Demolish and remove existing concrete crosswalk areas at 3rd Avenue.
    • Install conduit for future crosswalk signaling enhancements.

April 22nd - April 26th

  • Demolished the existing concrete crosswalk area at 3rd Ave and the concrete island on Main Street.
  • Completed the installation of the remaining 1 ½" conduit supplying the RRFB's, along with the ¾" conduit crossing 3rd Ave.
  • Sidewalks were poured in front of State Farm, half of the Level 11 frontage, and the ADA ramp at the SE corner of 4th Ave by LaRusso.
  • Lowered the irrigation vault at Ace Hardware.
  • Prepped sidewalk areas for upcoming concrete work.
  • Focused on temporarily paving the trenches created on Monday.
  • Started foundation transition work at Yo Treats, with additional attention required.
  • Planned activities include placing 12" storm lines to connect various catch basins along the west side of Main Street.
  • Global Electric will be onsite to pour RRFB foundations and the metered pedestal base.

April 29th - May 3rd

  • Wrapped up the 12" storm run from Conoco to City Hall
  • Abandoned existing irrigation vault near 3rd Ave
  • Potholed utilities in front of Yo Treats
  • Started catch basin run from manhole #4 near Yo Treats to Catch basin near Kristy's
  • Poured sidewalks in front of Level 11
  • Prepped ADA's at NE/NW 3rd Ave
  • Roughed in channels on manholes #4 and #5
  • Installing manhole #1
  • Prepping for final storm runs leading to manholes #2 and #3
  • Laid out asphalt cut lines for future work

Important Information:

  • Parking along Main Street will continue to be disrupted during work hours. We apologize for any inconvenience this may cause and appreciate your understanding.
  • The lot adjacent to Sol Tapatio will be cleaned up to divert traffic from the Sol Tapatio drive-through in preparation for future construction work.
  • Phase 1 is 3rd to 4th Ave (heading South)
  • Phase 2 is 4th Ave to the Highway (heading South)
  • Phase 3 is Jeremy Loveless to 4th Ave (heading North)
  • Phase 4 is 4th Ave to 3rd Ave (heading North)